In what order should concrete finishing tasks be completed?

Prepare for the NASCLA Commercial Construction Exam. Enhance your skills with flashcards and multiple choice questions, each featuring hints and explanations. Ace your exam with confidence!

The order of concrete finishing tasks is crucial for achieving a smooth and durable surface. Starting with screeding is essential as it involves leveling the freshly poured concrete to the desired elevation and creating an even surface. This initial step lays the groundwork for all subsequent actions.

After screeding, the next step is floating, which helps to compact the surface and fill in any low spots. Floating also helps to bring excess water to the surface, which is important for the final finish.

Following floating, edging is performed to create clean lines and define the edges of the slab. This task serves both aesthetic and functional purposes, as it helps to prevent chipping at the edges when the concrete cures.

Finally, troweling is the last step. This process creates a smooth, hard surface by applying pressure with a trowel. It is typically done after the concrete has begun to set but is still workable. Troweling enhances the appearance of the surface and adds to its strength.

This sequence—screeding, floating, edging, and troweling—ensures that each step supports the next, leading to a well-finished concrete slab.