What does the phrase 'start to start with a 7-day lag' refer to in construction scheduling?

Prepare for the NASCLA Commercial Construction Exam. Enhance your skills with flashcards and multiple choice questions, each featuring hints and explanations. Ace your exam with confidence!

The phrase 'start to start with a 7-day lag' refers to a construction scheduling scenario where one task can begin as soon as another task has started, but there is a specified delay of 7 days before the second task can commence. This type of relationship between tasks allows for some degree of overlap while also incorporating a lag time, which can be crucial for managing resources or dependencies in a project.

In construction scheduling, having such a lag can help in planning the workflow more effectively. It acknowledges that even though one task has started, there are reasons (like needing certain preparations or resources) that prevent the second task from starting immediately. This is important in ensuring that tasks are sequenced effectively without conflicts or resource shortages as the project moves forward. The delay allows time for certain preliminary steps or preparations to be completed on the initial task before the following task begins.

Other options do not accurately reflect this concept. For example, discussing two concurrent tasks needing to wait for one to begin does not align with the idea of one task starting soon after another but with a lag. Therefore, understanding that the phrase indicates a controlled delay after the start of an initial task is key to proper scheduling in construction.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy