When considering labor costs, what external factors must an estimator evaluate?

Prepare for the NASCLA Commercial Construction Exam. Enhance your skills with flashcards and multiple choice questions, each featuring hints and explanations. Ace your exam with confidence!

When determining labor costs, it is essential for an estimator to evaluate expected efficiency and concurrent activities because these factors significantly influence how effectively labor resources are utilized on a project. Expected efficiency refers to how productive the labor force is anticipated to be, which can be affected by their skill levels, experience, and the type of work being performed. If a crew is expected to work efficiently, labor costs may be lower since tasks can be completed more quickly.

Concurrent activities also play a crucial role, as the presence of multiple tasks happening at the same time can either increase labor demands or lead to delays. For example, if several trades are working in the same area, this can complicate coordination and may require additional labor or specialized scheduling to prevent downtime. By assessing both efficiency and concurrent activities, estimators can develop a comprehensive understanding of how labor costs will be impacted throughout the duration of the project.

In contrast, focusing solely on a contractor's hourly rate does not account for variations in efficiency, skills, or working conditions, which can lead to underestimated labor costs. While potential risks and weather conditions are important for planning, they do not directly integrate into labor cost estimation itself. Similarly, material delivery schedules, though critical for overall project timelines and planning, do not provide direct

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy